-
TeraWulf Announces October 2023 Production and Operations Updates
المصدر: Nasdaq GlobeNewswire / 02 نوفمبر 2023 16:37:33 America/New_York
Self-mined 314 BTC in October for a total of 2,744 BTC mined year-to-date.
Continued to participate in multiple demand response programs at the Lake Mariner facility.
EASTON, Md., Nov. 02, 2023 (GLOBE NEWSWIRE) -- TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), owners and operators of vertically integrated, domestic bitcoin mining facilities powered by more than 91% zero-carbon energy, today provided an unaudited monthly production and operations update for October 2023.
October 2023 Highlights
- Self-mined 314 bitcoin in October with an average production rate of over 10 bitcoin per day.
- After a planned outage during the first week of October, achieved greater than 95% of targeted self-mining operational hash rate.
- Power cost averaged $10.8k per bitcoin produced, or approximately $0.034/kWh in October.
Key Metrics 1 October 2023 Bitcoin Self-Mined 2 314 Value per Bitcoin Self-Mined 3 $29,527 Power Cost per Bitcoin Self-Mined $10,813 Avg. Operating Hash Rate (EH/s) 4 5.0 Management Commentary
“During October, the Company mined 314 bitcoin, a slight decrease from September’s bitcoin production, due to unfavorable network factors including a substantial 9.3% month-over-month increase in network difficulty,” said Sean Farrell, SVP of Operations at TeraWulf.
“As we continue to improve operational excellence across the fleet, our Lake Mariner facility is pursuing increased participation in demand response programs to further establish ourselves as an asset to the grid. We have recently undergone a slight reorganization of site resources aimed at maximizing miner inventory and slot utilization. Current construction activities at Lake Mariner’s Building 3 remain on schedule for completion by year-end, with the first pod of Hydra racks already installed earlier this week,” added Farrell.
Production and Operations Update
On October 2, Lake Mariner entered a planned outage to transition from a temporary substation feed to a permanent feed. During the outage, approximately 1.4 EH was offline for 4.25 days. Lake Mariner returned to full operations on October 6 and operated at +95% of targeted self-mining capacity for the remainder of the month.
As of October 31, 2023, the Company had an operational miner fleet of approximately 50,000 of the latest generation miners, comprised of 34,000 miners at its wholly owned Lake Mariner facility in New York (5,000 of which are hosted pursuant to an agreement expiring in the fourth quarter of 2023) and 16,000 self-miners at the nuclear-powered Nautilus facility in Pennsylvania.
About TeraWulf
TeraWulf (Nasdaq: WULF) owns and operates vertically integrated, environmentally clean bitcoin mining facilities in the United States. Led by an experienced group of energy entrepreneurs, the Company currently has two Bitcoin mining facilities: the wholly owned Lake Mariner Data facility in New York, and Nautilus Cryptomine facility in Pennsylvania, a joint venture with Cumulus Coin, LLC. TeraWulf generates domestically produced Bitcoin powered by 91% zero carbon energy resources including nuclear, hydro, and solar with a goal of utilizing 100% zero-carbon energy. With a core focus on ESG that ties directly to its business success, TeraWulf expects to offer attractive mining economics at an industrial scale.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as “plan,” “believe,” “goal,” “target,” “aim,” “expect,” “anticipate,” “intend,” “outlook,” “estimate,” “forecast,” “project,” “continue,” “could,” “may,” “might,” “possible,” “potential,” “predict,” “should,” “would” and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf’s management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) conditions in the cryptocurrency mining industry, including fluctuation in the market pricing of bitcoin and other cryptocurrencies, and the economics of cryptocurrency mining, including as to variables or factors affecting the cost, efficiency and profitability of cryptocurrency mining; (2) competition among the various providers of cryptocurrency mining services; (3) changes in applicable laws, regulations and/or permits affecting TeraWulf’s operations or the industries in which it operates, including regulation regarding power generation, cryptocurrency usage and/or cryptocurrency mining, and/or regulation regarding safety, health, environmental and other matters, which could require significant expenditures; (4) the ability to implement certain business objectives and to timely and cost-effectively execute integrated projects; (5) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to growth strategies or operations; (6) loss of public confidence in bitcoin or other cryptocurrencies and the potential for cryptocurrency market manipulation; (7) adverse geopolitical or economic conditions, including a high inflationary environment; (8) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (9) the availability, delivery schedule and cost of equipment necessary to maintain and grow the business and operations of TeraWulf, including mining equipment and infrastructure equipment meeting the technical or other specifications required to achieve its growth strategy; (10) employment workforce factors, including the loss of key employees; (11) litigation relating to TeraWulf, RM 101 f/k/a IKONICS Corporation and/or the business combination; and (12) other risks and uncertainties detailed from time to time in the Company’s filings with the Securities and Exchange Commission (“SEC”). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in the Company’s filings with the SEC, which are available at www.sec.gov.
Company Contact:
Jason Assad
Director of Corporate Communications
assad@terawulf.com
(678) 570-67911 Unaudited monthly results are based on estimates, which remain subject to standard month end adjustments. The Company’s share of the earnings or losses of the Nautilus facility is reflected in the caption “Equity in net loss of investee, net of tax” in the consolidated statements of operations. Accordingly, operating results of the Nautilus facility are not reflected in revenue, cost of revenue or cost of operations lines in TeraWulf’s consolidated statements of operation.
2 Includes BTC earned from profit sharing associated with a short-term hosting agreement at the Lake Mariner facility and TeraWulf’s net share of BTC produced at the Nautilus facility.
3 Computed as the weighted-average opening price of BTC on each respective day the Self-Mined Bitcoin is earned.
4 While nameplate inventory for WULF’s two facilities is 5.5 EH/s, inclusive of gross total hosted miners, actual monthly hash rate performance depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair.